Jersey Central Power & Light (JCP&L), a subsidiary of FirstEnergy Corp., has completed equipment inspections and maintenance across its central and northern New Jersey service area in preparation for the summer season. The measures aim to enhance the reliability of the electric grid amid high temperatures, storms, and potential hurricanes.
Doug Mokoid, President of FirstEnergy's New Jersey operations, stated: "Our maintenance and inspection programs are designed to ensure that we can provide the safe and reliable electric service our customers need to keep cool and comfortable during the hot, stormy summer months, and to meet the demands on our system that accompany the influx of seasonal tourism in our service territory."
Helicopter patrols have surveyed over 700 miles of high-voltage transmission lines this spring. These inspections are intended to identify issues such as damaged wire or broken crossarms that are not visible from ground level. Identified reliability concerns are promptly addressed.
In addition, JCP&L utilized thermovision cameras to capture infrared images of electrical equipment. This technology allows detection of potential problems within substations and on power lines that may not be apparent during regular visual inspections. Bright colors or "hot spots" in these images indicate possible equipment issues, prompting detailed inspections and repairs to prevent future outages.
Preparations also include readiness for severe weather events predicted by the National Oceanic and Atmospheric Administration (NOAA). NOAA forecasts an 85% chance of an above-normal hurricane season with up to 25 named storms, including up to seven major hurricanes.
Critical equipment like mobile substations has been strategically positioned near Jersey Shore communities to address higher electricity demand due to tourism. In northern New Jersey, flood walls at substations prone to river overflow have been tested for effectiveness.
Customers can manage their electric bills during high-temperature periods by following several tips provided by JCP&L:
- Use fans efficiently.
- Close drapes or blinds on sunny windows.
- Utilize programmable thermostats.
- Seal leaks with caulk or weather stripping.
- Check air conditioner filters regularly.
- Avoid using heat-producing appliances during peak hours.
Assistance programs are available for customers needing help with their electric bills through firstenergycorp.com/billassist.
JCP&L serves 1.1 million customers across multiple counties in New Jersey. Updates can be followed on social media platforms X (@JCP_L) and Facebook (facebook.com/JCPandL).
FirstEnergy operates one of the largest investor-owned electric systems in the U.S., serving customers across several states including Ohio, Pennsylvania, New Jersey, West Virginia, Maryland, and New York. The company's transmission subsidiaries maintain approximately 24,000 miles of transmission lines connecting various regions.
For more information or media inquiries: Chris Hoenig at (609) 350-8599; Investor inquiries: Gina Caskey at (330) 761-4185.